Baustellenbericht: Sanieren unter dem königlichen Theater – Kanalsanierungs Blog

Construction site report: Renovation under the royal theater – Sewer renovation blog

We are back with a short blog post! Our technician Dennis was allowed to go to Greece to support the construction site and was thus able to gain exciting insights into renovation in other countries 😉
Damage situation: Crack with excavation and rising seawater at approx. 9.5m; pipe DN 350

“Monday morning; Thessaloniki airport:

I was warmly welcomed by the managing director of Ydrofili. After visiting the office and getting to know the renovators, we visited the construction site on Monday afternoon.

The municipal utilities were supposed to dismantle the affected pipe on Tuesday at 09:00, but due to the rain the sea level rose and the amount of water in the pipe unfortunately postponed our project to an uncertain time.

So as not to sit idly by, we have already cut off the Flex 3D DN350 (5.5 mm) and prepared the AIRBAGLINER® DN350 and the fire hose to go with it. We have also already attached the liner to the vacuum pump.

At 8 p.m., the time had finally come and the municipal utilities were able to remove the pipe. After cleaning with the chain and flushing, a camera inspection could be carried out.

We wasted no time and started mixing the resin straight away. Naturally, we used Bodenbender EP170 resin so that we didn’t have to stress ourselves too much: Everything runs a little more relaxed in Greece! 😉

The liner, now weighing approx. 100 kg, had to be lowered by crane on a pallet to the pipe 3 m below. We then installed it by hand with finesse and sufficient lubrication using the Flutsch ground mover!”

“Immediately after installation, we then inverted the AIRBAGLINER® in combination with the fire hose. Because we were standing with the inversion drum approx. 1 m away from the pipe and the AIRBAGLINER® was filled with water here, we supported it with pallets. We set the pressure to 0.8 bar to counteract the seawater and were able to start exchanging air for water at 22:00.

As we only had one tap there, this took a correspondingly long time. But pretty much at midnight we were able to start heating up with the help of the Bodenbender Thermobox! We decided that 3 men from Ydrofili and I would stay on site to keep an eye on the water level and pressure. The inlet temperature of 90°C was not reached in the return pipe due to its length, where it was a maximum of 62°C.

After hours of waiting, a pizza at 02:00 and lots of fun conversations, the liner was hardened at 05:30. To cool it down slowly, we connected a pressure control valve, pressurized it with compressed air, set it to 0.8 bar and let it cool down until 15:30.

After the subsequent removal of the AIRBAGLINER®, we cut off the excess liner and carried out a camera inspection.

The liner looked great and the construction site could be left successfully.

To celebrate this, we all met up in the late afternoon for ouzo, beer and delicious food by the sea 😊”suck, built in by hand!”

Thanks to the Ydrofili team for the insights into Greek renovation!

See you next time,

Your Dennis

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies).

You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.

Scroll to Top