Building site report: two SteamBoxes and our robot Moppel on the job in Gütersloh – sewer renovation blog

Before our block heads off for a short break – remember the BODENBENDER PROGRESS WEEKS start next week – we have another building site report for you!
We were on a job with the team from Sanierungstechnik Dommel GmbH in Gütersloh in February and had the opportunity to try out something a bit different again… have a read and see for yourself.

It all started in the morning the industrial area of Gütersloh: Top of the agenda was the renovation of a DN 300 concrete sewer. The starting point was on the premises of a local company and led under a road along to the company carpark opposite, leaving roughly 30m to be renovated.

The necessary materials and machinery were unloaded; at the same time the sewer was cleaned and inspected with the camera. After getting the green light we got going – the pipeline was free and ready for renovation.

The FlexLiner (5mm DN 300) and the AIRBAGLINER® were measured up to match. The vacuum on the liner was activated and thus prepped for the resin. At the same time another piece of DN 50 AIRBAGLINER® was prepped for the large Ø 950 mm carbon drum for the steam circuit. Setting was to be done with two SteamBoxes.

Our ImpregnationRobot was deployed too and an extra generator to ensure sufficient power.

But it wasn’t until this point that we mixed the resin. Despite it being EP 170 we stepped things up a little when it came to the quantity required: at the same time we used two cup stirring tools to stir in parallel so suspended particles etc. were well mixed and the hardener well incorporated.

The resin was poured into the liner gradually and finally impregnated evenly using the ImpregnationRobot. Back and forth a few times – our application engineer Michael was visibly enjoying himself!
Together, the 30m Flexliners were wound onto the drum and brought to the shaft. First the inliner was installed – open end – and then the AIRBAGLINER.®

After everything was where it should be at around 1 p.m., the two SteamBoxes were finally connected, and the setting could start. After about 10-15 minutes, the approx. 105°C in the inlet had been reached and after about 30 minutes it was roughly 85°C in the return flow, too.

After cooling, the camera inspection was carried out around late noon/afternoon, bringing our construction site trip to a successful end.

Thanks to the team at Dommel for having us. It was our pleasure to be able to help out!

Until next time,

Your renovation team

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies).

You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.

Scroll to Top